540 Clearing & Earthwork

We were brought on by Flatiron Gurgatos to clear 120 acres for the future I-540 development. Strategic access and tight timelines made this a high-visibility site, and our team delivered with precision and speed.

SCOPE OF WORK

Cubic yards of dirt moved
0
Total Acreage
0

Key Scope Highlights

  • 644,000+ Cubic Yards of Dirt Moved
  • Mass earthwork operations totaling over 640,000 cubic yards, including long-haul sequences across multiple haul zones and Poole Road crossings.
  • Clearing and grubbing of 120 acres along the future six-lane, high-speed toll corridor from Rock Quarry Road to I‑87/US 64/US 264
  • Removal of trees, stumps, brush, and surface debris, delivering a clean, build-ready site for Flatiron’s grading and roadway construction.
  • Executed on varied terrain with environmental sensitivity, preserving required buffers and maintaining erosion control per NCDOT standards.
  • Coordinated closely with Flatiron’s field team to meet aggressive schedule milestones, keeping progress on track toward the planned 2028 opening.

More Projects

dji fly 20260415 093446 643 1776275284371 photo scaled

Elliott Farms

dji fly 20260402 155858 540 1775567023565 photo scaled

Merritt Reserve

dji fly 20260413 153546 616 1776176719870 photo scaled

Gatsby Station

is being added to the cart...